中铁十四局集团隧道工程有限公司
由于场地及工期等因素影响导致盾构机到达接收里程后,无法进行正常的拆解及吊出,需在洞内对盾构机进行拆解分块,倒运至始发井吊出。结合北京地铁19号线草桥站~右安门外站区间盾构到达拆解施工实践,盾构机从风井始发井始发,到达右安门外站后,盾构机主机与后配套台车各线路断开;预先在右安门外站底板铺设轨道用于暂储分块盾体,在中板预留孔洞安装分解盾体用行架装置;盾构机各部件的拆解、存放、运出顺序紧密相连,在有限的空间内完成盾构机主机零部件从始发端运出。
盾构机;暗挖地铁站;站内解体;土压平 衡盾构